Our leadership team's overall To-Do completion rate drops below ninety percent specifically because one department head consistently completes only half of their assigned weekly tasks, claiming operational firefighting always takes precedence. How do we address this individual bottleneck in the Level 10 Meeting™ without turning the To-Do review into a public disciplinary hearing?
When one person consistently drags down your To-Do completion rate, you do not have a meeting problem. You have an accountability or capacity problem. The ninety percent standard exists because weekly commitments are the primary engine of traction.
During the To-Do review, the rules are rigid: each item is either done or not done. There is no explanation, no justification, and no storytelling permitted during the five-minute review. If the department head has five tasks and three are not done, the score is reported accurately. Do not turn the review into a public interrogation. That burns time and breeds defensiveness.
Instead, as soon as the review concludes, drop a single item onto the Issues List: department capacity or task execution. When you reach that topic in IDS®, solve the root cause. Ask direct questions:
- Is this leader taking on To-Dos that belong to their direct reports on the Accountability Chart?
- Are they committing to tasks that cannot realistically be finished in seven days?
- Does this seat lack the tools, automation, or staff needed to keep operations moving?
If the leader claims that firefighting prevented them from finishing their work, they are working in the business instead of on their seat. Either they do not GWC™ their role, or their department processes are broken.
Fixing the root cause in IDS® protects the dignity of the room while keeping the ninety percent threshold non-negotiable. If the pattern continues after providing support, it becomes a personnel decision, not a weekly agenda debate.