Our weekly To-Do review takes forever because team members are bringing long-term operational projects onto the list and giving weekly updates on them, rather than keeping To-Dos strictly limited to short-term, seven-day tasks. How do we clean up our To-Do list to stop project status reporting?

When multi week projects creep onto your weekly To-Do list, your five minute review will quickly devolve into a slow, administrative status report. A Level 10 Meeting™ is designed to maintain a high speed operational pulse, not to act as a project management tracker.

To stop this, you must enforce a strict definition of a To-Do. In the EOS® framework, a To-Do is a highly specific action item that can and must be fully completed within seven days. If a task requires more than two weeks of work, it is either a quarterly Rock or a larger operational initiative that must be broken down into individual, weekly, bite sized To-Dos.

During the five minute review, the only acceptable status updates are "Done" or "Not Done." If a team member starts explaining their progress, the facilitator must cut them off immediately.

If a To-Do is not done, it stays on the list for one more week. If it is still not done after two weeks, it must be dropped to the issues list to IDS® why it is stuck. This simple discipline keeps your meeting fast and highlights resource bottlenecks. Never allow a leader to list a project like "Optimize marketing funnel" as a weekly To-Do. Instead, the To-Do must be "Draft outline for funnel copy." Keep the steps small, keep the timelines to seven days, and you will eliminate meeting waste instantly.