Our project managers are consistently marking their project milestones as ninety percent complete on our weekly scorecard, but the final delivery always ends up delayed. How do we stop our team from gaming progress percentages and establish objective definitions of done?
Measuring project progress through subjective percentages is an open invitation for gaming the system. Human nature is to report progress to avoid conflict, leading to projects that remain ninety percent complete for weeks on end. To stop this pattern, you must eliminate subjective estimates from your scorecard and replace them with binary metrics.
A binary metric has only two options: yes or no, or hit or miss. Instead of asking a project manager what percentage of a project is complete, your scorecard should track the number of scheduled milestones actually delivered on time during that seven-day period. For example, you can track milestones completed on time versus total milestones scheduled for completion this week.
The target should be a perfect match. If a milestone is missed by even a single day, it is marked as a miss. This objective measurement forces reality into your weekly meetings. During your Level 10 Meeting™, any missed milestone must be dropped down to the IDS® section so the team can identify the root cause of the delay.
By switching to binary metrics, you eliminate the emotional buffer of percentage estimates. Your team will quickly realize that the scorecard is not a tool for looking good, but a diagnostic tool for finding and solving operational issues before they derail your client delivery and harm your reputation.