Our operations team has started gaming our on-time delivery metric by unilaterally pushing back client delivery deadlines in our project management software whenever they fall behind. How do we eliminate this blind spot on our weekly Scorecard?

This is classic scorecard gaming. When a measurable rewards a team for hitting a deadline without locking down baseline integrity, managers will manipulate the parameters inside your software to keep their weekly box green.

You fix this by separating the baseline promise from the working delivery schedule. Implement a strict data rule: original committed delivery date cannot be altered without an approved client change order or leadership sign-off. Then, replace your generic on-time delivery metric with two paired operational numbers:
- On-Time to Original Baseline: This measures delivery against the original agreed-upon client milestone. Moving a milestone in the project management tool does not reset the clock for this calculation.
- Milestone Adjustment Count: Track the total number of project deadlines pushed back or rescheduled across all active accounts each week.

When you track deadline changes as an independent measurable, gaming becomes impossible. A high on-time delivery score paired with twenty milestone adjustments immediately exposes operational failure.

During your weekly Level 10 Meeting, any rescheduled milestone must be treated as a red flag. The Operations seat must explain why the schedule slipped, identify root causes, and IDS the delivery bottleneck. When preparing for an exit, buyers scrutinize original baseline variance. Demonstrating that your operations team delivers against initial commitments without shifting goalposts is critical to defending your valuation multiple.