Our team-wide To-Do completion rate has dropped into the 70 percent range for a month. How do we diagnose whether this is an accountability issue, an over-commitment problem, or a structural capacity bottleneck?
Consistently dropping below the 90 percent target on To-Dos is a system failure. When three out of ten weekly commitments fail to get done, execution stalls and Rocks inevitably slip.
To diagnose the root cause, do not guess. Put To-Do Completion on the Issues List and look at the numbers across three distinct filters:
- Individual accountability vs. team capacity. Check whether the misses are isolated to one or two leaders, or distributed evenly across the entire table. If one seat is at 50 percent while everyone else is at 95 percent, that leader either lacks personal execution discipline, has poor time management, or does not GWC their seat. If every leader is sitting at 70 percent, the team is suffering from an over-commitment problem driven by poor scoping during IDS.
- Scope and clarity. Review the past four weeks of incomplete To-Dos. If items are phrased as massive projects rather than simple seven-day actions, your team is using the To-Do list as a dumping ground for mini-Rocks. A To-Do must be binary and executable within seven calendar days. If it requires multiple handoffs or external approvals, break it down to the next immediate action step.
- Unaddressed firefighting. If leaders are consistently pulled away by day-to-day emergencies, you have an operational capacity or delegation problem. The business is reliant on leadership heroic intervention because tribal knowledge has not been documented and transferred down.
Run these three checks during your next pulse to isolate the real issue, assign corrective action, and hold the 90 percent line.