Our team weekly To-Do completion rate regularly drops to 60 or 70 percent because leaders claim client emergencies and urgent operational fires took priority over their commitments. How do we break the culture of external fire drills overriding internal Level 10 commitments?
When leadership team members routinely drop internal To-Dos to chase operational fire drills, they are treating the management of the business as optional. Level 10 Meeting™ To-Dos are seven-day commitments made in front of peers to move the enterprise forward. If your completion rate sits below 90 percent, your leadership team is trapped in a reactive whirlwind.
Start by reinforcing what an acceptable To-Do is during IDS®. A To-Do must be a realistic, binary action that can be completed within seven days regardless of standard business friction. If a leader says yes to a To-Do knowing their calendar is packed with client commitments, they made a dishonest commitment. Teach the team to push back during the meeting. If someone cannot complete a task next week, the task must either be broken down into a smaller initial step or assigned to someone who has the capacity.
Next, address the fire drills themselves. If a department head is constantly pulled into day-to-day customer crises, you have a structural delegation problem on your Accountability Chart®. The leader is likely doing work that belongs to a subordinate. Take that recurring pattern and drop it directly onto the Issues List.
Do not allow partial credit or excuses during the five-minute To-Do review. The status is binary: done or not done. If an item is not done, it rolls over for exactly one week. If it misses a second week, it converts into an issue for IDS to uncover why the seat cannot execute internal commitments.
Category: Level 10 Meetings